News

New pipelines rolling out across our district

by
February 07, 2018

MORE than 19km of pipelines will be installed across the Goulburn-Murray Irrigation District in coming months, with works expected to create significant water savings in the region.

The $2 billion Goulburn-Murray Water Connections Project plans to construct 16 pipelines during the irrigation season, in consultation with landowners, as part of its early works schedule.

Works are currently being carried out or completed on 10 of the pipelines — installing a total of almost 12km — in three irrigation districts:

■Rochester – four pipelines totalling more than 7.5km

■Torrumbarry – three pipelines totalling more than 3km

■Murray Valley – two pipelines totalling more than 1km.

Meters and regulators will also be upgraded along the pipelines at the same time.

Traditionally, pipeline works were carried out during the winter works period; however the project is now undertaking works throughout the year to increase efficiencies in reaching water savings targets.

Minister for Water Lisa Neville said the Connections Project is delivering an improved water supply to our agricultural communities, modernising the irrigation district and providing a huge boost to local economies.

“These critical crucial works are ensuring we deliver an efficient irrigation system that supports irrigators in regional Victoria into the future,” Ms Neville said.

Project director Frank Fisseler said completing works during the irrigation season means more landowners will be connected to the modernised delivery network sooner.

“We are modernising the delivery network to supply water more efficiently and generate water savings that contribute to the long-term sustainability of Victoria’s water supply,” Mr Fisseler said.

These works are being carried out by John Holland, which was appointed under the Reset Delivery Plan.